Chapter 13: Roof Trusses
1. Introduction
Installing the roof trusses is an exciting project. Both roof
trusses and sheathing (described in the next chapter) can be installed
in one day by an experienced crew. Most of the work is off of the
ground. Only workers who are comfortable with heights should install
trusses. Volunteers with medical conditions or who take medication
which causes dizziness should not install roof trusses. Other projects
can be found on the ground.
If building a one story house, the gable ends may be assembled on
the ground. A crane may or may not be used to get the trusses onto the
roof.
2. Safety Issues
- Review the Morning Safety Huddle Talking Papers for Roof Work
with the Volunteers.
- No walking on the cap plate of the exterior or interior framing.
- All workers who are working off the ground should be comfortable
working at heights and not have any medical condition making this
unsafe.
- No one should be working beneath crews working above the ground
because of the risk of falling materials. If someone must be below,
they should wear a hard hat.
- Ladders should have firm footing and be at a safe angle. A
coworker should support the ladder at the bottom whenever a worker is
mounting or dismounting a ladder.
- Workers should be certain that they only step on secure
structures.
- Power tools should only be used by people trained in their safe
use.
- Eye and ear protection should be used when using power tools.
3. Prior Tasks to Have Been Completed before Beginning
- Exterior walls have been straightened
- Cap plate on all framing
- Beams on porch are temporarily braced before stepping on them (if
applicable)
- Materials ordered and on site
4. Recommended Staff/Crew Assignments
- A crew of 3 - 4 gable ends (if applicable)
- 2 crew of 5 to raise trusses
- 2 crews of 4 to prepare and install fascia board
- A crew of 3 to be the saw crew, one cuts the others stabilize and
transport materials.
5. Order/Tasks to be Completed
____Build ladders on interior walls to support walk boards
____Layout truss locations on cap plate
____Build gable ends (if applicable)
____Trusses lifted to top of house
____Trusses raised, secured, and braced
____2 x 4's nailed to side walls to act as trusses (on two story house)
____Trim tails of trusses if needed
____Trim and install fascia board
____Build returns (if applicable)
____Frame attic access (if applicable)
6. Tools/Equipment List
- Extension ladders
- Step ladders
- Walk board
- Hammers
- Circular saw
- Table Saw (optional but useful)
- Tape measures
- Pencils
- Speed square
- Carpenter's square
- String
- Extension cords
- Saw horses (2)
- Hand saw
7. Material List
- Trusses
- 2 x 4's (longest lengths available)
- Nails 16d, 8d
- ½" sheathing
- Truss braces
- Truss clips
- Hurricane braces
8. Quality Checkpoints
____Gable end is assembled and sheathed (if applicable), vent hole
cut out
____Proper layout for trusses on cap plate
____Trusses raised, secured, and braced properly
____2 x 4's nailed to side walls to act as trusses (on 2 story)
____Fascia board installed correctly
____Hurricane braces installed correctly so they will not interfere
with drywall
____Attic access framed properly (if applicable)
____Returns built properly (if applicable)
9. Construction Drawings and Text
NOTE: The following drawings, diagrams, and text are to be used on
the job site when a question arises as to methods and procedures
associated with the task. The notes on the drawings have been geared
toward use as a quick reference. If a more in-depth explanation is
needed, please read the text description. But most importantly, consult
your Habitat Site Supervisor and Construction Manager for advice as
needed.
Cap plate layout
The cap plates should be marked with the locations of the trusses. This
will be done similarly to laying out the exterior walls, except that
the trusses will be marked with 24" on center rather than 16" on
center. Layout should be done from the end of the house specified in
the plans. The cap plates of the hall walls should also be marked.
Assembling gable ends (if applicable)
The gable ends are assembled on the ground and will be lifted into
place later by a crane. The gable truss should be laid on a level flat
surface. 2 x 4 material is nailed to the back of the bottom of the
truss so that it is flush with the bottom. It should be nailed so that
the 3 ½" surface extends back from the bottom of the truss. This
surface will lay on the top of the cap plate and will be used for a
nailing surface. It will also overhang the cap plate and be used to
screw the ceiling drywall.
A string should be used to ensure that the bottom chord of the truss
which will sit on the cap plate is straight and stays straight. The
gable truss is sheathed with ½" sheathing nailed every 8" with
8d nails, 6" on the perimeter. If the gable end is to receive blue
board, it is a good idea to install the blue board now rather than
after the gable end has been installed. The seams in the blue board
should not coincide with the seams in the sheathing. The front gable
truss should not be sheathed where the porch trusses will tie to allow
for circulation. The porch gable end is done in the same manner.
Assemble a ladder assembly with one 2 x 6 and one 2 x 4 connected by
short 2 x 4's every 2 feet. It should be the width of the
overhang. The assembly is nailed to the front of the gable
truss. The 2 x 6 will be the fascia board. Nail this ladder
assembly to the front of the gable truss.
A hole may need to be cut in the sheathing at the peak for the
crane. Check with the HFHSTL construction staff.
Installing the Gable End (if applicable)
The gable end will be lifted to the top of the house with a crane. Once
lifted, volunteers will need to position the gable end so that the
front of the blue board on the gable end aligns with the blue board of
the exterior wall. If blue board will not be installed, then the
sheathing is aligned. The gable end is then centered, measuring the
overhang of the tail on either side of the house. It is nailed in place
every 12 inches with 16d nails.
Raising trusses
It is very useful to use walk boards when installing the trusses. The
walk boards will be run perpendicular to the direction of the trusses.
There should be one on either side of the house and one down the
center. Use 2 x 4 bracing nailed into the wall framing to build bracing
on which to place the walk boards. As the bracing will support the walk
boards and the people on them, use as many braces as possible and make
sure all are securely nailed.
The trusses will be stacked on the top of the house using the crane.
They can be lifted manually, but this is uncommon. Prior to raising any
of the trusses, the gable end needs to be installed on the one story
houses. The crane will lift it into place. The tails should have equal
overhang on both ends. Nail through the 2 x 4 that was nailed to the
bottom chord of the gable truss into the cap plate every 12" with 16d
nails. The second truss will need to be secured as described below.
On the one story house, there are several methods to align the
trusses the entire length of the house. One method is to pull a string
from the tails of both gable trusses and align the tail of each truss
with that line. Another method is to place each truss at the location
of the marks and center the truss so that it has equal overhang on
either side. Each truss should be raised individually by a crew of 3
people. On each side wall it is secured by toe nailing 3 16 d nails. If
the truss crosses interior walls, a clip is installed which will attach
to both the truss and the cap plate. These slotted anchor clips will
allow the truss to float or move up and down with changing atmospheric
conditions. This will reduce drywall cracks in the corners between the
walls and the ceilings. If unfamiliar with these clips, ask HFHSTL
staff for instruction. Between each pair of adjacent trusses, bracing
is installed. 22 ½" brackets are attached using a hammer. Make
sure that the trusses are pulled completely together prior to securing.
Attach 2 brackets between each set of trusses on each side, at one
third intervals. If these brackets are not available, use 1 x 3 or 2 x
4 material marked 24" on center and nailed with 1 8d or 16d nail (leave
the head up for easy removal) into the top of each truss. These boards
would need to be removed as the sheathing is applied.
On two story houses, the trusses are stood in place and nailed with
3 16d nails. At one end the truss will likely be attached to a wall.
Blocking may need to be installed so that the truss can be nailed into
the wall, again with three nails. Trusses will probably not be used
next to the walls. If this is the case, 2 x 4's will be nailed to
the wall framing. Determine the location by determining the front and
back elevation from another truss. Snap a chalk line using these
dimensions. Nail the 2 x 4 with two 16d nails into each wall stud.
Bracing the trusses All bracing will come with a
bracing pattern determined by the manufacture. As the trusses are
installed, temporary bracing is used and then permanent bracing is
added according to the plan.
On the one story house, the gable truss should be temporarily braced
once installed. A 16' 2 x 4 is cut with a 45 degree angle at one end
and nailed near the top into the side of one of the supports near the
middle of the gable truss. It is then anchored to a solid support, most
likely the hall wall. The bottoms of the next few trusses should be
moved toward the gable truss and the 2 x 4 should be fed through these
trusses so that the trusses may be raised without removing the bracing.
After the trusses are all raised, a 2 x 4 can be nailed across the tops
of the bottoms of the trusses and the long 2 x 4 can be cut and
anchored to this. An alternate method of temporarily bracing the gable
end is to brace it to the outside of the house. Two 16 foot 2 x 4's are
overlapped and nailed together. One end is nailed to a stake and the
other to the gable truss. Permanent bracing is put inside the house
after the trusses are all up.
As each truss is raised it should be braced. Use metal braces to
align and secure each truss to the previous truss. The braces should be
placed at thirds on the trusses. Make sure to pull the trusses tight to
both ends of the brace prior to hammering it into the trusses. If this
is not done, the mistake will be translated throughout the trusses and
may produce additional problems. If the metal braces are not available,
mark a 1 x 3 or 2 x 4 for the trusses at 24 inches on center and nail
to the top of the trusses.

Fascia board
On the one story house, the fascia board on the side of the house is
cut from 2 x 6 lumber. An edge must be cut with a slope approximating
the pitch of the roof. This cut can be made with a circular saw by a
skilled worker but is more accurately cut on the table saw. The fascia
board is then nailed into the tails of each truss with 3 16d nails so
that the sloped edge is flush with the top of the trusses. The first
board should be butted up to the overrun of the fascia board on the
gable end and can also be nailed. The fascia board should be cut so
that any cuts fall at the midpoint of the tail of a truss. This way,
both sections of fascia board can be nailed to the truss. When all the
fascia board is attached, cut the overrun from the gable end fascia
board.
Returns
Returns will be needed on the one story houses. On each tail of each
gable end, a return needs to be built. This will ensure a continuous
line of soffit material the entire length of the house and is
aesthetically pleasing. It should be built from 2 x 6 material. See
diagram for building instructions.
Attic access
If applicable, an attic access should be framed at the end of the hall.
2 2 x 4's should be cut to 22 ½". These should be nailed between
2 adjacent trusses forming a square.
Printer-friendly versionPage last updated 5/1/2005.
|